The management of PT Masmindo Dwi Area (MDA) had an audience with the Acting Governor of South Sulawesi, Prof. Zudan Arif Fakrulloh, on Thursday, August 1, 2024, at the South Sulawesi Governor’s office.
On that occasion, MDA’s CEO Trisakti Simorangkir reported the progress of the Awak Mas gold mining project managed by MDA in Ranteballa Village, Latimojong District, Luwu Regency, South Sulawesi. “Up to now, the process of compensating for the remaining land continues and is approaching the final stage, so the production plan, which was previously set for 2025, is estimated to be postponed to 2026,” said Trisakti.
The change in the production schedule target is due to several obstacles in the land compensation process, as well as natural disasters of floods and landslides in Luwu Regency last May, which resulted in the disruption of access roads in several villages, thus affecting MDA’s operational activities at the site.
The Acting Governor provided guidance and support for the efforts made by MDA. It is hoped that in addition to the land compensation process, the preparation of the construction phase can also be carried out gradually, so that MDA can eventually start production. It is expected that once MDA begins production, it will make a significant contribution to improving the welfare of the community and the development of South Sulawesi, especially in Luwu Regency. (DY)
Source: masmindo.co.id
Read the full storySitemap
Our Portfolio